Su-Tong Bridge will shake hands on the instant |
|
|
|
|
Written by Ralf Mostert
|
|
Saturday, 28 April 2007 |
 Su-Tong Bridge The building of Su-Tong Bridge which attracts the whole world focus turns into the last stage of sprint. By yesterday, the main bridge of 2088 meters only leaved the last 192 meters; The building of inclined pull-line leaved the last 24 pairs; The south-north bridge approach and the incidental bridge with 6118 meters will complete the concrete mould of the last two bridge floors at the beginning of May; It foresees that the main bridge will realizes the gather in June; The bitumen and concrete pave of the bridge floor will complete before 1 October. So The victory of opening to trafic of the Su-Tong Bridge in the next spring is within sight. As record, It foresees that the main bridge, south-north bridge and the incidental bridge of Su-Tong Bridge will realize the run-through of whole bridge. Source: http://www.suzhou.gov.cn